King Charles III England Coast Path (KCIIIECP) Project at Nore
Barn Woods/Warblington Road Foreshore - April 2025
Following
the
approval of
this
stretch of
the KCIIIECP by
the
Secretary of
State
(SoS) in
July 2024, the project team have been reviewing
the points raised in the Planning Inspector’s report
and
working on ensuring
that
the following key points
are
addressed as
part of the project:
·
Designs need to
improve accessibility
(ramps)
and
have non-slip
surface
·
Designs need to
facilitate access at
all
states of
predicted
tides
·
Inclusion of extra
information boards to
warn
users that
in
extreme
weather the
path may be inundated in storm conditions
·
Markers or barrier to
be
installed to
show
edge of
path
·
Works on the culvert/bridge
to be
subject to a Flood risk activity
permit
(FRAP)
·
Screening to be
offered
to all leaseholders along
the
seawall
·
The Slipway/path
alongside dingy park should
not be
blocked
·
A
roped off
area
would be
included along the foreshore
in
order to
reduce
the trampling of this
section
of the shoreline and
to
allow
saltmarsh/vegetation
to
establish/re-establish.
·
The Planning Inspector
dismissed
concerns
over
privacy,
potential
change in
value
of adjacent properties, the project’s value for money,
possibility of sea debris being deposited
upon
infrastructure, and
how the project may
impact
the amount
of
time the path can be used considering the existing
public right of way follows the same route and the
improved accessibility/safety of the proposals will offer
significant benefits to local walkers and KCIIIECP users.
Design
Change
Requests
Since
the
decision by
the SoS, the
KCIIIECP
project
team
received a
request
from
Maisemore Gardens Ltd to add extra protection to the
existing boardwalk design as a way to help protect the
existing seawall. The suggested design was of ‘gravel’
type boards set in the surface
of the foreshore,
affixed to
the
boardwalk
piles closest
to the
seawall and backfilled with shingle/rejects. This design
element has been considered by the project team – see
more under ‘Boardwalk’ below.
The preliminary designs showed that
the ‘ramp’ of the existing walkway would be removed and
the
boardwalk
butted up
to the
end of
the
walkway. MGL
requested
that
rather than
the ramp being removed a short section was added
to the ramp to square it off. This design element has
been considered by the project team – see more under
‘Boardwalk’ below.
In
addition,
the
project team
also
received
requests from
locals
to remove
the
handrail from
the boardwalk design and to replace this with a small
up-stand/toe board. This design element has been
considered and accepted by the project team.
Included
with
this note
are
updated
preliminary
designs that
include
the
above
requests. These designs are for
the
purposes of
the
procurement process, they
are
not final
design drawings. The winning contractor, through
the competitive procurement process, will undertake
their own designs/specification and therefore these
designs are subject to
change.
Culvert/Path
Surfacing
Works
The
outline
designs,
for
raising the
level of the
path
and repair
of the culvert, will
be used
as the basis of a design and build request for
tender/quote via a HCC Framework for contractors. This
is standard procurement practice for projects like this
and HCC procurement
team
recommended
this as
the
next stage
in this
project.
This
means that
final designs will be supplied by the winning
contractors based on their individual methods of working
as part of the procurement process.
Once
tenders
have been
received
and
assessed, HCC
will
apply to
Natural
England for
the KCIIIECP establishment grant and contractors
will be appointed once the grant has been
approved.
Once
contractors have been
appointed, we will
make
public any
details
of the
final
design that are not commercially sensitive.
The
information
from
the appointed
contractor
will be
used
for the
FRAP
application to
EA. Once an application is duly made EA have 2-4
months to determine whether to issue the
permit.
Once
the
permit has
been
issued work
can
commence on
site.
Currently we are
hoping
that we can start work during July but this is dependent
on the EA issuing the permit and we have included a
contingency until the end of October 2025 for this work
being completed.
The
Culvert/Path
Works
will include
but
not be
limited
to the
following:
·
Repair/replacement
of
broken
culvert
·
Raising of path
level above culvert to
meet
with current
highest
predicted
tides
·
Works do not
obstruct
vehicular
access
to Nore
Barn
Woods or
access
from the
private dingy park/slipway
·
Associated drainage from
fields/woods to the
north
of the
site
·
Handrail/safety
fencing
to stop people falling
off the
side
of the
raised
path
sections
·
Fencing of degraded
area
of foreshore to the
south
of the site to
reduce
footfall and
encourage revegetation of habitat
·
New path surface
to
encourage
responsible access to
the
west of
the
fenced area
extending from the raised path section to the path
towards the picnic bench.
·
The public footpath will be closed
and therefore public access will be restricted for short
periods of time whilst certain elements of the work will
be undertaken – contractor
to
determine
timings –
this will be
to
ensure the
safety
of both
the
public and the team working on site.
Boardwalk
The project team will undertake a
similar procurement process where contractors will be
asked to design and build the boardwalk. As with the
culvert works, final designs will be developed by the
contractor and again we will make public any details of
the final design that
are not
commercially
sensitive. The contractor’s
method
statement will
determine
the method of construction.
We
are
taking
forward the
design
request from
local
people to
remove
the handrail
and provide an upstand edge to the boardwalk.
Taking
advice
from other
authorities building similar
structures along the
KCIIIECP
has led to the recommendation of the use of ‘Polywalk’ boardwalk
materials -
https://polydeck.co.uk/polywalk/
. The justifications for using this
material include:
·
Lifespan (75 years)
in the
marine
environment
compared to
timber
(5-10 years)
·
Non-slip surface is
guaranteed again compared
to
timber or
recycled
plastic
·
Environmentally
friendly
– the boardwalk’s core
contains
140
recycled 500ml
plastic bottles per square metre, whereas
wood
preservatives can leach harmful and toxic contaminants
into the environment
·
Can be easily
un-screwed and re-fixed as
there is
no
warping/degradation
·
Lightweight – therefore
the
materials can
be
walked onto
site
reducing
potential vehicular damage to the foreshore
·
Meets and exceeds
standard
requirements
in
regards to
loading
capacity
·
Can be manufactured
to
size, off-site
meaning
that
installation is quicker
and easier
We have considered the request by MGL
to square off the end of the ramp by adding material
rather
than taking
any
away. We can
confirm that
the ramp will not
be
removed as
part of
the installation of
the
boardwalk. If
required
for
installation
purposes the
project
will add to the ramp if we can be assured that
doing so would not affect the integrity of the ramp
itself and that it can be affixed without any problems.
Before we
can
progress with
this
element of
the KCIIIECP
establishment
project we
need
to have received
written confirmation from Maisemore Gardens Ltd (MGL)/owners of the
seawall that
they wish the KCIIIECP project team to include the extra
protection (boards and backfill) into the boardwalk
design. If this is included, the complete removal of
the boardwalk will not be possible without this element
being lost.
The written confirmation
should include
that MGL/owners of the seawall will contribute the
additional
cost to
the
project
for the
inclusion
of
this work
and
that
MGL/owners
of the
seawall will assume full responsibility for the ongoing
maintenance of this element of the project. We
estimate the additional design and installation cost of
this element to be in the region of £10,000 but this
will be confirmed once prices have been obtained from
contractors. To note, KCIIIECP funds strictly cannot be
used towards this element of the boardwalk design as it
has been determined as a form of sea defence, which as a
principle the KCIIIECP does not fund. Following
completion of the project, HCC and the KCIIIECP will
only
be
responsible for
the ongoing
maintenance
of the
boardwalk
itself and
not the
additional protection element.
The written confirmation should be
sent to Alison Perry by 30th April 2025. If this is not
received by this date
the
KCIIIECP
establishment project will
progress
without the
additional protection, as detailed above.
If
MGL/owners of the
seawall
wish to
progress
with their
own works
to protect
the seawall
as outlined in the asset inspection note (AIN) included with
this email,, this should be completed prior to the
installation of the boardwalk. It is recommended in this
case that MGL/owners of the seawall seek advice on whether
planning permission/SSSI consent/harbour works licence
should be obtained from the relevant authorities.
As with the culvert works, we would be
looking to undertake the works in July, after/alongside
the
culvert works.
However,
we do
have until
the end
of October
to complete the works.
Other KCIIIECP
works
in
the
vicinity
As part of the establishment works along
the Hampshire part of the KCIIIECP SHE 2 (South Hayling
to East
Head 2)
stretch we
are hoping
to
re-surface
sections of
the public footpaths and
replace the old narrow gates with those that will meet BS
5709:2018. By undertaking this work we aim to improve
accessibility for those less mobile and make the inland path
between Warblington and Nore Barn Woods more attractive for
use thus reducing the impact of walkers and dogs on the
birds that nest and feed along the foreshore between Nore
Barn Woods and Langstone.
Opening of
South
Hayling
to
East Head
Stretch
of
KCIIIECP
This stretch of the KCIIIECP falls within
both Hampshire and West Sussex. Working with colleagues
in West
Sussex and
Natural
England we
are aiming that
coastal
access rights
will commence and the National Trail open in December
2025. This will mean that 265 continuous miles of KCIIIECP
between Calshot in the west
and Rye Harbour, East Sussex
in the east will be open for public use by the end of
this year.
Alison
Perry
King
Charles III
England
Coast Path
Project
Manager April 2025
CC.
Secretary
of
MGL
CC.
Cllr Lulu
Bowerman
CC.
Jake
Kendall-Ashton,
Natural
England
Download this update HERE