King Charles III England Coast Path (KCIIIECP) Project at Nore Barn Woods/Warblington Road Foreshore - April 2025
Following the approval of this stretch of the KCIIIECP by the Secretary of State (SoS) in July
2024, the project team have been reviewing the points
raised in the Planning Inspector’s report and working
on ensuring that the
following key points are addressed
as part of
the project:
· Designs need to improve
accessibility (ramps) and have non-slip surface
· Designs need to facilitate access at all states of predicted tides
· Inclusion of extra information boards to warn users that in extreme weather the path
may be inundated in storm conditions
· Markers or
barrier to be installed to show edge of path
· Works on
the culvert/bridge to be
subject to
a Flood
risk activity permit (FRAP)
· Screening to be offered to all leaseholders along the seawall
· The
Slipway/path alongside
dingy park should not be blocked
· A roped
off area would be included
along the foreshore in order to reduce the
trampling of this section of the shoreline and to allow saltmarsh/vegetation to establish/re-establish.
· The Planning Inspector dismissed concerns over privacy, potential change in value of
adjacent properties, the project’s value for money,
possibility of sea debris being deposited upon infrastructure,
and how the
project may impact the amount of time
the path can be used considering the existing public
right of way follows the same route and the improved
accessibility/safety of the proposals will offer
significant benefits to local walkers and KCIIIECP users.
Design Change Requests
Since the decision by the SoS, the KCIIIECP project team received a request from Maisemore
Gardens Ltd to add extra protection to the existing
boardwalk design as a way to help protect the existing
seawall. The suggested design was of ‘gravel’ type
boards set in the surface of
the foreshore, affixed
to the boardwalk piles closest to
the seawall
and backfilled with shingle/rejects. This design element
has been considered by the project team – see more under
‘Boardwalk’ below.
The
preliminary designs showed that the ‘ramp’ of the
existing walkway would be removed and the boardwalk butted up to the end of the walkway. MGL requested that rather than the
ramp being removed a short section was added to the ramp
to square it off. This design element has been considered
by the project team – see more under ‘Boardwalk’ below.
In addition, the project team also received requests from locals to remove the handrail from
the boardwalk design and to replace this with a small
up-stand/toe board. This design element has been
considered and accepted by the project team.
Included with this note are updated preliminary designs that include the above requests.
These designs are
for the purposes of the procurement process, they are not final design
drawings. The winning contractor, through the
competitive procurement process, will undertake their
own designs/specification and therefore these designs are
subject to change.
Culvert/Path Surfacing Works
The outline designs, for raising the
level of the path and repair of the culvert, will be used as
the basis of a design and build request for tender/quote
via a HCC Framework for contractors. This is standard
procurement practice for projects like this and HCC
procurement team recommended this as the next stage in this project. This means that final
designs will be supplied by the winning contractors
based on their individual methods of working as part of
the procurement process.
Once tenders have been received and assessed, HCC will apply to Natural England for the
KCIIIECP establishment grant and contractors will be
appointed once the grant has been approved.
Once contractors have been appointed, we will make public any details of the final design
that are not commercially sensitive.
The information from the appointed contractor will be used for the FRAP application to EA.
Once an application is duly made EA have 2-4 months to
determine whether to issue the permit.
Once the permit has been issued work can commence on site. Currently we are hoping that
we can start work during July but this is dependent on
the EA issuing the permit and we have included a
contingency until the end of October 2025 for this work
being completed.
The Culvert/Path Works will include but not be limited to the following:
· Repair/replacement of broken culvert
· Raising of path level
above culvert to meet with current highest predicted tides
· Works do not obstruct vehicular access to Nore Barn Woods or access from the
private dingy park/slipway
· Associated drainage from fields/woods to the north of the site
· Handrail/safety fencing to stop people falling off the side of the raised path sections
· Fencing of degraded area of foreshore to the south of the site to reduce footfall and
encourage revegetation of habitat
· New path surface to encourage responsible access to the west of the fenced area
extending from the raised path section to the path
towards the picnic bench.
· The
public footpath will be closed and therefore public
access will be restricted for short periods of time
whilst certain elements of the work will be undertaken –
contractor to determine timings – this will be to ensure the safety of both the public
and the team working on site.
Boardwalk
The
project team will undertake a similar procurement
process where contractors will be asked to design and
build the boardwalk. As with the culvert works, final
designs will be developed by the contractor and again we
will make public any details of the final design that are not commercially sensitive. The contractor’s method statement will determine the
method of construction.
We are taking forward the design request from local people to remove the handrail and
provide an upstand edge to the boardwalk.
Taking advice from other authorities building similar structures along the KCIIIECP has led to
the recommendation of the use of ‘Polywalk’ boardwalk
materials - https://polydeck.co.uk/polywalk/ .
The justifications for using this material include:
· Lifespan (75 years) in the marine environment compared to timber (5-10 years)
· Non-slip surface is guaranteed again compared to timber or recycled plastic
· Environmentally friendly – the boardwalk’s core contains 140 recycled 500ml plastic
bottles per square metre, whereas wood preservatives
can leach harmful and toxic contaminants into the
environment
· Can be easily un-screwed
and re-fixed as there
is no warping/degradation
· Lightweight – therefore the materials can be walked onto site reducing potential
vehicular damage to the foreshore
· Meets and exceeds standard requirements in regards to loading capacity
· Can be manufactured to size, off-site meaning that installation is quicker and easier
We
have considered the request by MGL to square off the end
of the ramp by adding material rather than taking any away. We
can confirm
that the
ramp will not be removed as
part of the installation of the boardwalk. If required for installation purposes the project will
add to the ramp if we can be assured that doing so would
not affect the integrity of the ramp itself and that it
can be affixed without any problems.
Before we can progress with this element of the KCIIIECP establishment project we need to
have received written
confirmation from Maisemore Gardens Ltd (MGL)/owners of
the seawall that they
wish the KCIIIECP project team to include the extra
protection (boards and backfill) into the boardwalk
design. If this is included, the complete removal of
the boardwalk will not be possible without this element
being lost.
The written confirmation should
include that MGL/owners of the seawall will contribute
the additional cost to the project for the inclusion of this work and that MGL/owners of the
seawall will assume full responsibility for the ongoing
maintenance of this element of the project. We
estimate the additional design and installation cost of
this element to be in the region of £10,000 but this
will be confirmed once prices have been obtained from
contractors. To note, KCIIIECP funds strictly cannot be
used towards this element of the boardwalk design as it
has been determined as a form of sea defence, which as a
principle the KCIIIECP does not fund. Following
completion of the project, HCC and the KCIIIECP will
only be responsible for the ongoing maintenance of the boardwalk itself and not the
additional protection element.
The
written confirmation should be sent
to Alison Perry by 30th April
2025. If this is not received by this date the KCIIIECP establishment project will progress without the additional
protection, as detailed above.
If MGL/owners of the seawall wish to progress with their own works to protect the seawall
as outlined in the asset inspection note (AIN) included with
this email,, this should be completed prior to the
installation of the boardwalk. It is recommended in this
case that MGL/owners of the seawall seek advice on whether
planning permission/SSSI consent/harbour works licence
should be obtained from the relevant authorities.
As with
the culvert works, we would be looking to undertake the
works in July, after/alongside the culvert works. However, we do have until the end of October to
complete the works.
Other KCIIIECP works in the vicinity
As part
of the establishment works along the Hampshire part of the
KCIIIECP SHE 2 (South Hayling to East Head 2) stretch we are hoping to re-surface sections of the public footpaths
and replace the old narrow gates with those that will meet
BS 5709:2018. By undertaking this work we aim to improve
accessibility for those less mobile and make the inland path
between Warblington and Nore Barn Woods more attractive for
use thus reducing the impact of walkers and dogs on the
birds that nest and feed along the foreshore between Nore
Barn Woods and Langstone.
Opening of South Hayling to East
Head Stretch of KCIIIECP
This
stretch of the KCIIIECP falls within both Hampshire and West
Sussex. Working with colleagues in West Sussex and Natural England we are aiming that coastal access rights will
commence and the National Trail open in December 2025. This
will mean that 265 continuous miles of KCIIIECP between
Calshot in the west and
Rye Harbour, East Sussex in
the east will be open for public use by the end of this
year.
Alison Perry
King Charles III England Coast Path Project Manager
April 2025
CC. Secretary of MGL
CC. Cllr Lulu Bowerman
CC. Jake Kendall-Ashton, Natural England
